Cambodian power [in Koh Kong] may arrive early [-Thai may protest against coal power plants built inside Thailand]

Egat expects delays in local coal plants

Tuesday February 05, 2008
YUTHANA PRAIWAN
Bangkok Post


The Thai-developed Koh Kong power plant in Cambodia will likely begin supplying electricity earlier than scheduled because of delays facing other plants planned by the Electricity Generating Authority of Thailand (Egat).

According to Egat deputy governor Suttipong Teppitak, the state utility has accelerated negotiations with the operators of the 3,660-megawatt, coal-fired Koh Kong plant, a venture of Italian-Thai Development, Ratchaburi Holding and Egco Group.

''We will speed up a deal so that we can sign a power purchase-agreement a bit early,'' he said.

Egat fears that protests against its own coal-fired power plants could delay their startup and possibly create a risk of power shortages in the future.

Mr Suttipong said there was very limited time to educate the public about new clean-coal technology, but public acceptance would be essential before Egat started construction.

''We must have a reserve plan to deal with any incidents since it seems that anything could happen in our country,'' said Mr Suttipong, who oversees policy and planning.

Egat had planned to begin receiving power from Koh Kong between 2019 and 2021. Egat's local coal-fired plants, with a total 2,800 MW, were to start serving the grid in 2015-17. ''We will swap our schedules,'' he said.

Egat is in the process of site selection and preparing a public acceptance plan.

The Koh Kong talks, said Mr Suttipong, would focus on power tariffs and the high cost of a 500-kilovolt line running 500 kilometres from the west coast of Cambodia to Bangkok.

The Koh Kong operators were unavailable for comment.

An Energy Ministry source said Egat would also open talks with operators in Burma and southern China as optional power sources.

Egat recently has approached South China Grid Co about buying 1,750 MW initially. The project is due to come online in 2010 with a capacity of 10,000 MW.

Monday, January 07, 2008

More hydropower plants sought [in Thailand]

Monday January 07, 2008
YUTHANA PRAIWAN
Bangkok Post

The Electricity Generating Authority of Thailand (Egat) will propose that the new government approve the building of new hydro-electric plants countrywide, says Suttipong Teppitak, deputy governor for policy and planning at the state utility.

''Based on our research, Thailand still has potential to build 4,000 megawatts of hydro-electricity at many sites across country,'' he said.

Mr Suttipong said hydro-electricity was one of the best choices for sustainable energy and was very cost-competitive. It can also help alleviate climate change problems, something plants using fossil fuels cannot do.

However, even hydro-electric dams are likely to encounter opposition from environmental activists, who have succeeded in blocking some coal-powered plants and are gearing up to oppose the government's nuclear-power plans as well.

The newest hydro-electric plant in Thailand is the Pak Moon Dam in Ubon Ratchathani, which opened in 1993 and has been the target of local fishermen and other activists ever since.

Mr Suttipong said Egat had identified appropriate sites for hydro-power, including 240 megawatts on the Pai River in Mae Hong Son, 56 MW at Sai Buri in Narathiwat, 80 MW on the Kaeng Krung River in Surat Thani, and huge potential on the Yom River in northern Thailand.

Egat is now installing electricity generators at its six mini-dams nationwide, which were built to ease the threat posed to farmers by floods. They also generate a combined of 78 MW of power.

Mr Suttipong said that clearing a forested area for a hydro-power plant represented less damage to the environment than what was caused by emissions from a similar-sized plant using fossil fuels.

Egat points to the success of its 30- year-old Bhumibol dam plant, where electricity production costs are only 0.60 baht a kilowatt-hour (unit) compared to 1.80 baht for a coal-fired plant and 2.20 baht one fuelled by natural gas.

But it is not clear whether the new government will continue to pursue the policies of its predecessor, or what kinds of fuels policymakers will favour.

Egat also will seek to amend parts of the national power development plan (PDP) to reflect an increase beyond its original projections for power supplies from neighbouring countries, based on new power purchase agreements.

According to the revised PDP, imports from neighbouring countries would total 14,600 MW, which accounts for 25.4% of total power capacity. The figure includes 7,000 MW from Laos, compared with 2,000 MW planned originally.

Egat is also counting on having 4,000 MW available from the huge Salween dam in Burma, starting between 2017 and 2020. As well, the coal-fired Koh Kong plant in Cambodia is scheduled to deliver 3,600 MW between 2019 and 2021.

The revised plan will still call for 4,000 MW supplied by a nuclear plant starting in 2020-21, and 1,400 MW from independent power producers in a new round of bids for power supplies to start in 2017-19.

Wednesday, December 12, 2007

Thailand provides electricity to Siem Reap and Banteay Meanchey

11 December 2007
By Ros Dina
Cambodge Soir Hebdo

Translated from French by Luc Sâr

At the end of November, Siem Reap and Banteay Meanchey provinces were connected to the Thai electricity grid. Battambang will be soon connected to this grid also. The exponential growth of tourism in Angkor explains this measure.

EGAT, Thailand’s national electricity company, provides electricity to two northwestern Cambodian provinces: Banteay Meanchey and Siem Reap. Starting since 26 November, this connection will grow even larger as the province of Batttambang will be connected to this grid soon. According to Cheam Kosen, director of the Siem Reap branch of the Cambodia Electricity Authority (CEA), this connection is the result of a convention concluded between the Cambodian and the Thai governments.

Cheam Kosen indicated that Siem Reap now has at its disposal 30 Megawatts (Mwh) of electricity. According to the electricity department officials in the province, only 16 Mwh was used between 26 and 29 November in downtown Siem Reap. This low consumption was due to mild weather condition.

15,000 consumers living in downtown Siem Reap and within a radius of 2 kilometers from downtown, use this electricity. On the other hands, the 11,500 homes in the province of Banteay Meanchey – which sees less tourists than Siem Reap – consumes less than 2.6 Mwh.

In Cambodia, the price of electricity in the provinces is higher than that in Phnom Penh due to the lack of generators and difficulties in the distribution of electricity in rural areas… Families rather wait patiently for Electricité dur Cambodge (EDC) to install the needed infrastructures covering the entire country, rather than relying on private distributors – most of the time, a single distributor in each rural area – whom they believe the cost to be too high.

“This new network will improve the living condition of the people. The price of electricity will decrease. Currently, the cost of a kilowatt comes to 1,220 riels (~$0.31),” said On Sum, the governor of Banteay Meanchey province. Sou Phirin, his colleague in Siem Reap, displays similar confidence. He declared that, recently, “numerous hotel owners have applied to use Thailand’s electricity.”

In spite of the authority’s optimism, the price decrease cannot be felt yet. However, electricity price seems to remain stable. In Siem Reap, the cost of 1 kilowatt of electricity is 870 riels (~$0.22).

“To date, I did not receive anything from the CEA to formalize a possible price change yet because we are still in a trial period,” said the director of the provincial electricity department. To find out more, Cambodge Soir Hebdo tried to reach the CEA president, but we didn’t have any luck.

According to the EDC Siem Reap office director, local companies – ASK and CTPC (Cambodia Power Transmission Lines Co. Ltd.), as well as the South Korean Sou Ching Company – manage the pwerline extension to the border line. Sou Ching also holds an authorization from the Apsara Authority to provide electricity to Zone I and II of the Angkor conservation area. Thanks to the arrival of this energy source, the Siem Reap electricity department will now be able to cover a more substantial customer base. “From now until 2012, Siem Reap will need more than 50 Mwh of electricity, because the city keeps on growing. New constructions go up like mushrooms!” Cheam Kosen said.

Monday, November 05, 2007

Thailand is mulling the construction of a nuclear power plant

Egat chief says nuclear power necessary

(BangkokPost.com) – The governor of the Electricity Generating Authority of Thailand (EGAT), Kraisri Karnasutra, has warned of a possible shortage of natural gas to produce electricity within the next three to four years.

The EGAT chief admitted to concerns that the construction of a nuclear power plant in Thailand could spark future protests but insisted that the move was necessary.

“We only have so much natural gas to produce electricity,” he warned. “We have noticed that supplies have dwindled and natural gas supplies could run out within 3 or 4 years.”

“I guarantee that modern day technology will create a perfectly safe environment to accommodate the use of nuclear power in our country as it has already done so in other countries.”

Thailand is one of 77 countries exploring nuclear energy as an alternative source of energy.

According to the Director of the International Atomic Energy Agency (IAEA), Mohamed ElBaradei, there are currently 439 nuclear power reactors in 30 countries, which supply 15 per cent of the world's electricity.

Friday, November 02, 2007

Cambodia coal plant planned

Friday November 02, 2007
POST REPORTERS
Bangkok Post


The Electricity Generating Authority of Thailand plans to co-invest in a new coal-fired power plant in Cambodia to source 3,000 megawatts under a project worth up to US$4.5 billion.

The new project is in line with Egat's plan to diversify its power sources across the region.

Acting Egat governor Santi Sarntijaree said the state enterprise was negotiating with potential investment partners.

''We expect the Chinese government will hold the largest stake. Other stakeholders will be Cambodian authorities and Egat,'' he said.

Under the agreement, Egat would buy all of the electricity generated from the project.

The project would require investment of $4.2 to $4.5 billion, or 142.8 to 153 billion baht.

The figure assumes an average cost of $1.4 million per megawatt.

The electricity from the project is scheduled to link with the Thai national power grid after the completion of the Hongsa lignite project.

Mr Santi said that the project is the first energy collaboration between Thailand and Cambodia after long negotiations.

Previously, the two governments discussed a smaller 1,400-1,600 mw project, but decided on a larger project for cost reasons.

''To buy power from neighbouring countries is our top choice to secure power to meet Thailand's growing demand, particularly in case we are unable to build more power plants,'' he said.

However, power supplies from neighbouring countries still account for less than 20% of total power generation in Thailand.