Cash dries up for tourism development in Asia [-Did the Russians developpers lie to Hun Sen about development on schedule?]

January 28 2009
Financial Times (UK)

The bridge linking Koh Puos island to the Cambodian mainland is under construction, but the timetable for building a yacht club, shopping centres, villas and hotels is under review as global credit markets dry up and international travel slows.

"We had hoped to finish everything by 2016, but we are probably now thinking more in terms of 2019 or 2020," says Oleg Khaidarov, construction director for the $900m (€682m, £635m) project intended to challenge established Thai beach resorts and make Cambodia a draw for more than the Angkor Wat ruins.

In a best-case scenario, executives such as Mr Khaidarov say projects will benefit from lower construction costs. But for tourism developments in Vietnam, Macao and elsewhere in Asia in early financing stages, the outlook is gloomier.

"Some big funds were very interested in our project but now everybody just wants to keep their money safe," says Kieu Lam, an official with Saigon SunBay, a Vietnamese seaside tourism development expected to cost $525m, of which only $25m has been committed.

In the absence of private funding, the Asian tourism sector is hoping to secure more government support.

Tuesday, January 27, 2009

Preah Sihanouk (formerly Sihanoukville): Name change from KPIG to Heritage Island Cambodia Investment (HICI)


27 Jan 2009
By Leang Delux
Cambodge Soir Hebdo

Translated from French by Tola Ek

Click here to read the article in French


The Russian director of the Koh Puos Investment Group (KPIG) met with Hun Sen on Monday 26 January. If the development project seems to be on a normal course, the name of the project appears to be a problem [Does it remind people too much about Russian PIGs?].


Alexis Chipa, KPIG director, told Hun Sen during his meeting that “the construction project is progressing as planned. The project was shown in Hong Kong where it attracted a lot of interest and curiosity. The construction site will be completed in 14 months. Currently, we are setting up the beaches. In spite of the world crisis, there is no stoppage or slowdown of the work.”

Alexis Chipa also asked Hun Sen to allow him to change his company’s name to Heritage Island Cambodia Investment (HICI) which is more attractive for luring tourists. Chipa also proposed to Hun Sen to set up a coordination committee to facilitate the progress of the project.

Hun Sen agreed to the two proposals.

The development project for a tourist resort, at a cost of $300 million, will also include the building of a 900-meter bridge linking the island to the coastal land. The inauguration of the project was conducted by Hun Sen on 07 January 2008.