Showing posts with label Kamchay. Show all posts
Showing posts with label Kamchay. Show all posts

Tuesday, January 29, 2008

Hun Sen's "battery of Asia" dams are serious threats to people

Cambodia's biggest hydropower dams serious threats to people

Mon, January 28, 2008
By Supalak G Khundee
The Nation (Thailand)


The construction of Cambodia's first and second biggest hydropower dams pose serious threats to eco-systems and the livelihood of thousands people in southwest of the country, an environmental conservationist report said Monday.

Under an aid package of $600 million(Bt18.6 billion) from China, Cambodia is constructing the Kamchay Dam with an installed capacity of 180 Megawatts (MW) the biggest in Cambodia in the southwestern Kampot Province and the 120 MW Stung Atay Dam in Pursat Province.

The Kamchay Dam developed by China's largest hydropower developer, Sinohydro Corporation, is located wholly within the Bokor National Park and will flood 2,000 hectares of protected forest, according to a research report by the US-based conservationist International Rivers.

The project, to be completed by 2010, denied access to nontimber forest products to local residents, for whom many is an important source of income, and potentially a negative impact on a local tourist resort downstream of the dam, it said.

The Stung Atay, constructed by Yunnan Corporation for International Techno Economic cooperation, will be completed by 2012. The dam will flood a substantial area of the Central Cardamom Protect Forest, the report said.

"Cambodia's free flowing rivers and abundant natural resources are invaluable assets, the health of which are vital to the wellbeing of Cambodia's rural population," said Carl Middleton, Mekong Program Coordinator with International Rivers.

"Poorly conceived hydropower development could irreparably damage these resources and undermine Cambodia's sustainable development."

At present, only 20 percent of households in Cambodia have access to electricity. It is expected that the soaring demand for electricity will increase to more than 900 from the 212 MW in 2002.

The government has many hydropower projects under feasibility study, including the Sambor Dam to be built in the mainstream of the Mekong River in Kratie Province with a capacity of 465 or 3500 MW depending on the design and size of the reservoir.

The Sambor Dam, if built, would block major fish migrations and could decimate the income of tens of thousands of subsistence and commercial fishers. The dam also threatens the habitat for the endangered Irrawaddy Dolphin, around which a thriving local tourism industry has grown.

The Ministry of Industry, Mine and Energy estimated the country has the potential to generate approximately 10,000 M, of which more than 50 percent will come from the Mekong mainstream.

Cambodian Foreign Minister Hor Namhong told an investment conference in Tokyo recently that his country has a great potential to generate electricity supplies for the region. Apart from Laos, Cambodia could be the "battery of Asia", he said.

The report recommends that Cambodia adopts international best practices in electricity planning, including the findings of the World Commission on Dams, which is widely recognised to be the international standard for energy and water planning.

"Cambodia has many choices for meeting our electricity needs including renewable and decentralised energy options that must be explored," said Ngy San, Deputy Executive Director with the NGO Forum on Cambodia.

Friday, March 09, 2007

China transforms Cambodia's electricity

By Cheang Sokha
Phnom Penh Post, Issue 16 / 05, March 9 - 22, 2007

Chinese companies are bringing a huge change to Cambodia's electricity supply, transforming it from dependence on local generators to a nationwide grid of hydroelectricity. Three power stations are being built now, and another three are planned.

Youn Heng, Deputy Director of the Evaluation and Incentive Department at the Council for the Development of Cambodia (CDC), said China is the main engine for Cambodia's hydropower development, and is investing huge capital compared with other countries.

"We can see that many hydropower development projects are from China," Heng said. "China has invested nearly a thousand million dollars in this sector."

He said China had invested in building a hydroelectric power plant at Kirirom in Kampong Speu, the $280 million Kamchay dam in Kampot, and a $400 million hydropower dam on the Steung Atai in Koh Kong province.

Heng said that besides hydropower, Chinese companies had invested in a variety of projects, such as infrastructure, textiles, mines and agriculture.

Bun Narith, Deputy General Director of the General Department of Energy at Ministry of Industry, Mines and Energy (MIME) said that on February 9 the Council of Ministers contracted the China Yunan Corporation for International Techno-Economic Cooperation to develop the Steung Atai hydropower dam. And the Yunan Southeast Asia Economy and Technology Investment Industrial Co Ltd has been contracted to install electricity transmission lines from the Steung Atai to Phnom Penh, Kampong Chhnang and Pursat, and to Battambang, Banteay Meanchey and Siem Reap provinces.

Narith said a Steung Atai feasibility study is nearly complete and dam construction will begin soon.

"The firm will take four years for the development and will produce 120 megawatts," Narith said, "The power link from Thailand to Siem Reap is not enough because the province is more developed and requires more power."

CDC's Heng said he had not seen the company proposals yet but had learned that the companies had signed a Memorandum of Understanding with MIME.

MIME's Narith said that besides the $400 million investment on the Steung Atai, the company is also studying the feasibility of building other dams in the area, near the junction of Koh Kong, Kampong Speu and Pursat provinces. These would be on the Steung Russei Chrum, Steung Chhay Areng and Steung Ta Tai. If these dams are built they and the Atai will produce 852 megawatts.

Son Dara, general secretary of Koh Kong province, said local people will receive adequate electricity from the project and it has the potential to attract more investment to the province.

Dara said a Japanese company had studied the feasibility of developing hydropower in Thmar Baing district and a Thai company of developing the Steung Me Teuk near the border.

"If approved by CDC they will produce 500 megawatts," Dara said.

Keo Remy, a Sam Rainsy Party parliamentarian, said Cambodians will have adequate electricity eventually, but the price will remain high because the capital investment in hydropower was high. Nevertheless, it should be cheaper than oil-produced power.