Saturday, July 05, 2008

Dammed if you do...

Friday, 04 July 2008
Written by Sovan Nguon The Phnom Penh Post

A hydropower dam being built in southwestern Cambodia will destroy more than 5,000 hectares of protected forests, say researchers who conducted an environmental assessment for the joint-venture’s Chinese partner.

The revelation was made by Um Serey Vuth, the leader of a team of researchers employed by the China Datang Corporation.

The corporation and its partners, CHD Cambodia Hydropower Development and Cambodia Power Grid, unveiled plans in May to invest $313.36 million to build the 120MW Atay dam, which is due for completion in 2012.

Serey Vuth, who headed a team of 10 researchers, said the assessment showed the dam would destroy 5,193 hectares of protected forests in the Phnom Samkok Wildlife Sanctuary and the Cardamom Mountains.

He said the assessment began in May, when work started on the project, and was completed late last month.

The assessment showed the dam would flood 3,650 hectares of protected forest in the wildlife sanctuary and 1,543 hectares of protected forest in the mountain ranges, he said.

He said trees had to be removed from the affected areas otherwise they would affect the quality of water in the dam.

Serey Vuth said, however, that the dam would have a minimal impact on people living in the project area and would bring much needed electricity to the Kingdom.

“Only 36 families in three villages in O’Som commune, Veal Veng district, Pursat province will be affected, along with about 1,000 fruit trees and 10 hectares of farmland,” said Serey Vuth.

He said the local authority and residents supported the project.

“The authority and the people support the project 100 percent because they will have access to the electricity generated by the dam," Serey Vuth said.

Seng Bunra, the country director of US-based NGO Conservation International, expressed qualified reservations about the project.

"For environmentalists, 5,000 hectares of protected forest is a lot if we are talking about preserving biodiversity, wildlife and habitats, and absorbing carbon dioxide," Bunra told the Post on July 3.

"But sometimes we need to make sacrifices because our country needs electricity and we just express our concerns.

"We can't prevent the government from developing the country but what we insist on with this project is protection for forests around the dam site to avoid further destruction," he said, warning that if this was not done up 10,000 hectares would be at risk of being cleared of trees.

He said that the Cardamom Mountains, which cover about two million hectares, is a unique eco-system in Cambodia containing rare wildlife such as tigers, elephants, wild buffalo, bears, Siamese crocodiles and dragon fish.

"In the Southeast Asian region, there is no protected forest as picturesque as those in the Cardamom Mountains," Bunra said.

Defending the project, Ith Praing, secretary of state for the Ministry of Industry, Mine and Energy, told the Post on July 3 that environmental damage was acceptable in hydropower projects because an adequate electricity supply was crucial for attracting foreign investment.

“Before allowing the development, we had to weigh its environmental impact and its contribution to development," he said.

"We see that development provides more advantages, so we decided to approve the project," Praing said, adding that improvements in electricity supply would also help to raise living standards.

“The more electricity is generated, the cheaper it will be, so there will be more foreign investors interested in doing business in Cambodia," he said.

Praing said the Atay hydropower project was one of three in protected forest areas in the Cardamom Mountains involving Chinese companies.

He said the two others were approved in mid-June. They are the China National Heavy Machinery Corporation's $540 million project to build the 246MW Tatay River dam, due for completion in 2013, and the 338MW Russey Chrum Krom project, involving an investment of $495.7 million by the Michelle Corporation, due to be finished in 2015.

Sam Rainsy Party lawmaker Yim Sovann said that while the country needed to generate more electricity, the government should do more to protect forests in areas adjoining project sites.

Thursday, January 31, 2008

It's not enough that China gave Cambodia the KR headache, now come the Chinese dams concerns also

Chinese Dam Projects Worry Environmentalists

By Mean Veasna, VOA Khmer
Original report from Phnom Penh
30 January 2008


At least two large Chinese companies have received investment licenses to take over hydroelectric projects in Cambodia.

Meanwhile, Chinese companies are studying four other projects, officials said recently. But the dams seriously threaten the environment, according to two groups that released a report Monday.

Cambodia fuel prices are higher than its neighbors in the region. Only 20 percent of the people living in downtown areas have enough electricity. The Cambodian government has said there is a clear need to lower electricity costs.

And the plan has encouraged private sector to produce and share electricity. But the investment in Cambodian hydroelectricity is threatening the ecological system and could affect thousands of Cambodian people, International Rivers and the Rivers Coalition in Cambodia said in a report, issued Monday.

The report says five Chinese hydroelectric companies, including Sinohydro Corporation and Yunan Corporation for International Techno-Economic Corporation, received government licenses to invest more than $500 million.

Three other companies had an agreement with the government to study four projects.

The report says the Kamchay hydroelectric project in Bokor National Forest, Kampot province, invested by Sinohydro, flooded 2000 hectares of forest.

Stung Chhay Areng, in the central Cadramom Mountains, could flood nine villages, affecting about 1,500 people, most of whom are ethnic minorities.

The project could flood the habitat of at least 31 animal species that are almost extinct. Meanwhile, a Sambo hydroelectric project in the Mekong basin would block the habitat and migration routes of fish species.

Ngy San is vice president of the NGO Forum of Cambodia and a member of Rivers Coalition in Cambodia.

He urged the government to initiate a clear national program and said the government had not studied the consequences of the project licenses.

“The report says those investments are mostly or totally made based on politics, which means the leaders of the two countries meet with each other,” he said. “They decided with the facilitation of the engineers. So, we request that the government should come up with a national program on the investment of local hydroelectric development.”

Several government environmental officials declined to comment on the report.

Ith Prang, secretary of state of the Ministry of Industry, Mines and Energy, said an impact study is conducted on every hydroelectric project, though some studies have not been concluded.

“We could not evaluate unless we have studied the environment around,” Ith Prang said. Officials in charge of commerce in the Chinese embassy in Phnom Penh refused to be interviewed to clarify the rivers report.

Kim Sovann, a spokesman for Sinohydro, said he had not seen the report of the above organizations. But he confirmed several studies were undertaken before his company received a license to invest.

“My company and the Ministry of Environment sent our staff to the site several times,” Kim Sovann said.

Ngy San said the investment could mean a surplus in Cambodian electric power in a couple of years, which would have environmental consequences and bring uncertainty in the sale of power to other countries.

But Ith Prang said the electric power production increase would be done yearly, according to actual need.

Tuesday, January 29, 2008

Chinese investment in dams threatens Cambodian eco-system: group

PHNOM PENH (AFP) — Cambodia's two largest dam projects threaten to flood huge swathes of protected forests, a conservation group has said, urging reform in the country's burgeoning hydropower sector.

International Rivers Network, in a report released late Monday, said that the Kamchay and Stung Atay dams, which seek to provide much-needed electricity to the country, will instead wreak havoc on local communities and slow development.

The US-based group targets in particular Chinese investment in the sector, which it said is powering forward through close ties between Cambodia's government and Beijing, unchecked by public scrutiny.

The projects highlight the "growing interest in large-scale hydropower dam development by Cambodian decision makers backed mainly by Chinese project developers and financiers," the group said.

"Chinese investment in Cambodia's hydropower sector is threatening some of the country's most precious eco-systems and the livelihoods of thousands of people."

Funded largely by a 600-million-dollar Chinese aid package, the Kamchay Dam is located entirely inside Cambodia's Bokor National Park and will flood 2,000 hectares of protected forest, the group said.

Once completed in 2010, it will also force local residents from the area, stripping them of their livelihoods, and could threaten downstream tourist sites, International Rivers said.

Protected forests in Cambodia's Cardamom mountains will also be submerged by the Stung Atay Dam, which is expected to come online in 2012, and four others currently under consideration.

"Cambodia's free-flowing rivers and abundant natural resources are invaluable assets," said Carl Middleton, Mekong program coordinator with International Rivers.

"Poorly conceived hydropower development could irreparably damage these resources and undermine Cambodia's sustainable development."

Only an estimated 20 percent of households have access to reliable electricity in Cambodia, one of the world's poorest countries.

Spiralling utility prices, driven by this lack of supply, are a major obstacle to attracting foreign investment, and the government has struggled to find a way to bring down the cost of power.

International Rivers urged Cambodia to seek alternate power sources, or adopt international standards within its own utilities sectors.

"Cambodia has many choices for meeting our electricity needs, including renewable and decentralised energy options that must be explored" said Ngy San, deputy executive director with the NGO Forum on Cambodia.

Hun Sen's "battery of Asia" dams are serious threats to people

Cambodia's biggest hydropower dams serious threats to people

Mon, January 28, 2008
By Supalak G Khundee
The Nation (Thailand)


The construction of Cambodia's first and second biggest hydropower dams pose serious threats to eco-systems and the livelihood of thousands people in southwest of the country, an environmental conservationist report said Monday.

Under an aid package of $600 million(Bt18.6 billion) from China, Cambodia is constructing the Kamchay Dam with an installed capacity of 180 Megawatts (MW) the biggest in Cambodia in the southwestern Kampot Province and the 120 MW Stung Atay Dam in Pursat Province.

The Kamchay Dam developed by China's largest hydropower developer, Sinohydro Corporation, is located wholly within the Bokor National Park and will flood 2,000 hectares of protected forest, according to a research report by the US-based conservationist International Rivers.

The project, to be completed by 2010, denied access to nontimber forest products to local residents, for whom many is an important source of income, and potentially a negative impact on a local tourist resort downstream of the dam, it said.

The Stung Atay, constructed by Yunnan Corporation for International Techno Economic cooperation, will be completed by 2012. The dam will flood a substantial area of the Central Cardamom Protect Forest, the report said.

"Cambodia's free flowing rivers and abundant natural resources are invaluable assets, the health of which are vital to the wellbeing of Cambodia's rural population," said Carl Middleton, Mekong Program Coordinator with International Rivers.

"Poorly conceived hydropower development could irreparably damage these resources and undermine Cambodia's sustainable development."

At present, only 20 percent of households in Cambodia have access to electricity. It is expected that the soaring demand for electricity will increase to more than 900 from the 212 MW in 2002.

The government has many hydropower projects under feasibility study, including the Sambor Dam to be built in the mainstream of the Mekong River in Kratie Province with a capacity of 465 or 3500 MW depending on the design and size of the reservoir.

The Sambor Dam, if built, would block major fish migrations and could decimate the income of tens of thousands of subsistence and commercial fishers. The dam also threatens the habitat for the endangered Irrawaddy Dolphin, around which a thriving local tourism industry has grown.

The Ministry of Industry, Mine and Energy estimated the country has the potential to generate approximately 10,000 M, of which more than 50 percent will come from the Mekong mainstream.

Cambodian Foreign Minister Hor Namhong told an investment conference in Tokyo recently that his country has a great potential to generate electricity supplies for the region. Apart from Laos, Cambodia could be the "battery of Asia", he said.

The report recommends that Cambodia adopts international best practices in electricity planning, including the findings of the World Commission on Dams, which is widely recognised to be the international standard for energy and water planning.

"Cambodia has many choices for meeting our electricity needs including renewable and decentralised energy options that must be explored," said Ngy San, Deputy Executive Director with the NGO Forum on Cambodia.

Friday, April 13, 2007

Chinese hydro firms move on Cambodian projects

13 April 2007
International Water Power & Dam Construction

Work has begun on the Stung Atay hydro power plant in Cambodia and a related transmission development.

The US$190M project is expected to produce some 465GWh annually while the transmission network, being constructed at a cost of US$113M, will connect Phnom Penh, Kampong Chhnang, Pursat and Battambang.

China Yunnan Corp for International Techno-Economic Cooperation and Yunnan Southeast-Asia Economy and Technology Investment Industrial Co are to develop both projects on a build, operate and transfer basis, Chinese state media reports.

Sunday, April 08, 2007

Chinese companies launch two power projects in Cambodia

April 08, 2007

Chinese companies here on Saturday launched two power projects in Cambodia, the Stung Atay hydropower plant and a set of electricity transmission network.

Cambodian Deputy Prime Minister Sok An and Governor of China's Yunnan Province Qin Guangrong, who is leading a delegation to visit Cambodia, unveiled the foundation stones of the two projects during a ceremony hold in Phnom Penh.

The hydropower plant costs 190 million U.S. dollars and can generate 465 million kilowatt-hour of electricity per year, according to a press release from the Chinese companies.

The power transmission network is constructed at the cost of 113 million U.S. dollars to connect Phnom Penh, Kampong Chhnang, Pursat and Battambang, it added.

China Yunnan Corporation for International Techno-Economic Cooperation and Yunnan Southeast-Asia Economy and Technology Investment Industrial Co., LTD. undertake the construction and development of both projects, the press release said, adding that the Cambodian government adopts BOT pattern (build, operate and transfer) for the projects.

Currently, Cambodia does not have the infrastructure to generate enough electricity to fuel the galloping demand, which has been rising 15 to 20 percent per year, according to Cambodian Ministry of Mines and Energy.

Source: Xinhua